Trackplan tweaks

 Now the baseboard is finalized, the track plan can be tweaked.




The yellow track is a passenger track that will operate on a shuttle schedule, leaving from the small station (nothing more than a rural stop really) an then going to the top right into a tunnel before it returns.

The orange track will be a programming track and the grey track the main goods track.

Everything is laid out on three levels. The uppermost level is the passenger track, the mid level is the switching yard for the goods track and the lower level is a small shadow track with a short parallel section so I can have trains running contineously in both directions.

On the right a part of the goods track branches off and goes up to a twin track that will be inside a removable diorama of a mine.

Some tweaks were necessary to make sure that the section with the double slip switch has enough clearance below the roof support that juts out upward through the baseboard (the white gap in the middle)

Next steps are to transfer the track plan to the baseboard and constructing the supports for the switching yard. The aim is to fully contruct the goods track before adding the passenger track. I am already looking at digital solutions, but for track testing purposes I can temporarily run an analog train.